New stretch target
Replace the incandescent downlighters and dimmers by LED low energy fittings. There are 9. (image unavailable)
Our Village Hall is of 70's construction with 70's insulation standards, we want to reduce the Energy waste and improve user comfort.*
Replace the incandescent downlighters and dimmers by LED low energy fittings. There are 9. (image unavailable)
Your community needs your help. Show your support and this project could be in with a chance of receiving a slice of Calor’s £85,000 funding pot. Projects receive 1 point for every like or share and 10 points when someone donates. Remember to log in or sign up for your points to count. Click here for more details.
Bishopstone Village Hall is used by all the local groups, clubs and societies for regular meetings and activities, children's parties, the village school and other ad-hoc events.
It is not very comfortable in the winter when the outside temperature drops below about 5 degrees C. (Particularly if there's one of those biting North Easterlies; seems to get into the very fabric of the Hall)..
Bishopstone Village Hall is a registered charity. A community resource administered by the trustees and a committee of management for the whole community. Population 693 (2011).
The committee consists of three Elected Members and up to Nine Representative Members from local clubs etc.
e.g BADS (Bishopstone Amateur Dramatic Society)
In addition to the 'provision and maintenance' regular social events are run by the committee to raise funds over and above the letting fees. e.g. A monthly Film Night (bring a cushion and a blanket).*
This objective of this project is to increase the level of insulation in the roof / ceiling to modern standards. It will benefit the community by:
1. Improving comfort levels in the winter.
2. Reducing energy use (running) costs.
3. Maintain the structural integrity of the roof.
Project Budget Estimate.
To improve the insulation levels to current standards we also have to ventilate the roof space to prevent condensation which also gives us the opportunity to carry out remedial work to the eaves roof felt, replace guttering and clad facias.
Main elements:
Insulation (additional 200mm) - main hall + Service area approx. 200m2
Eaves ventilated felt support repair trays. Replace facias and guttering.
Scaffolding.
VAT.
Total £8400